Case studies
Biotech
Helix AI
Helix AI

A protein-folding inference fleet moved north without a code change.

Helix AI serves structure predictions to drug-discovery teams around the clock. Moving to Narvik cut the carbon behind every query, with latency unchanged.

Industry
Biotech
GPUs
512
Site
N-01
Live since
April 14, 2026
A protein-folding inference fleet moved north without a code change.
Helix AI
N-01
−61%
CO₂ per query
0
Code changes to migrate
41 ms
Median latency to Frankfurt

Inference that never sleeps

Helix AI runs protein-structure prediction as a service for pharmaceutical and academic labs. Unlike training, the load never stops: queries arrive from Boston in the morning and Singapore at night, and the fleet runs close to full all day.

By late 2025 the fleet had grown to 512 GPUs on a grid where most of the power still came from gas. Customers started asking for the carbon behind each prediction, and the answer was not one Helix wanted to publish.

“Our customers measure everything. It was time we could show them the power, too.”

Same API, different latitude

Helix already ran on Kubernetes with the GPU operator, so the move was a matter of capacity, not code. Nordlys racked 512 H200s on N-01 and exposed them through the same cluster API. Helix shifted traffic one region at a time over two weeks, with the old fleet as a fallback.

What made it easy

  • Bare-metal nodes with the drivers and container runtime Helix already used.
  • A private 100 Gb/s link from Narvik to their edge in Frankfurt.
  • Per-minute power and PUE data, exported straight into their reporting.

Six months on

CO₂ per query is down 61%, and median latency from Frankfurt is 41 ms, well inside the 80 ms target. Helix now publishes the energy behind every prediction on its status page, measured at the meter in Hall A.

Biotech
“We changed one endpoint and moved 512 GPUs of inference to the Arctic. The models did not notice. Our sustainability report did.”
Jonas Weber
−61%
CO₂ per query
Jonas Weber
Helix AI
512
GPUs ·
N-01
02
Contact
Q1 2027 allocation is open

Your next run,
in Narvik.

Tell us cluster size and start date. An engineer replies within one working day.

Plan capacity